Construction continues to progress at Jamestown Road, with the ground floor slabs across all buildings now complete, alongside the construction of the ‘Golden Brick’ column for the new C3 affordable homes.

Work is continuing across the development, with the first floor slab progressing and Zones 1 and 2 now complete. Vertical elements are also progressing across the PBSA and Block C3 West, including works from the first to second floor along the Jamestown Road elevation.

Raised timber screening along the Arlington Road boundary is now complete, while environmental monitoring remains in place throughout the construction process, helping to minimise disruption to the local community while work progresses.


We look forward to sharing further updates as the project continues to move forward.